Client : Farab Co. Iran water and Energy Co.
Duration : 18 months
Location : 28 kilometer Izeh Road shahre kord
Topic of contract:
Karun 3 power plant is located in 28 kilometer from Izeh road to Shahr-e-Kord. Farab Co. and Iran water and Energy Co. were client and main client respectively.
The project included mobilisation, installation and pre commissioning of 8 Gas Bus ducts of Karun 3 power plant with related supports and equipments.
The above mentioned project started from the beginning of Oct. 2003.